AVE Mogente-Alcudia de Crespins
New high-speed railway access to Levante. Madrid-Castilla La Mancha-Comunidad Valenciana-Región de Murcia Section: La Encina-Játiva junction Phase I. Sub-section: Mogente-Alcudia de Crespins.
The Mogente-Alcudia de Crespins AVE project consists of the construction of nine viaducts, seven overpasses and four subways on a 17.5-kilometre section of high-speed double-track of Iberian gauge. La obra comprende la vía, electrificación e instalaciones.
In this Mogente-Alcudia de Crespins AVE project, 4.7 km of old tracks are used, bridges are restored and replaced by frames and viaducts, and masonry vaults are reinforced with frame/arch-type structures. The excavation is over 2,500,000 m3, and 5,225,300 kg of steel is used. .